Replacing Park House on the North Manchester General Hospital site is a new 150-bed adult mental health inpatient unit (AMHU), with associated access, parking, soft and hard landscaping. Cut and fill was required to create a development platform for the erection of the building.
Curtins produced a Materials Management Plan and supervised the works across a 12-week programme enabling re-use of approximately 17,240m3 of site won materials which would otherwise have been sent to landfill. Our environmental and geotechnical services on the £105m project included:
Phase 1 Preliminary Risk Assessment
Phase 2 Ground Investigation
Design Statement
Qualified Person Declaration
Earthworks Specification
Waste Classification
Part Time Supervision for 4 Months